What is three phase electricity?
Three phase electricity is a more powerful kind of mains supply than the single phase connection most homes and small premises have. It’s what workshops, garages and small manufacturers need when they run heavy kit such as large motors, welders or industrial pumps. If your business is planning to add that sort of equipment, three phase electricity is usually the first question to settle, before the machine arrives rather than after.
The upgrade itself is done by your local electricity network operator, not by your energy supplier or an electrician. The meter, though, belongs to your supplier. That split catches people out, so it’s worth understanding who does what.
When does a business need three phase electricity?
You need a bigger supply when the equipment you want to run needs more power than your current connection can carry. UK Power Networks, one of the regional network operators, says it can upgrade a single phase supply to a three phase supply, giving up to 70kVA of power, which it says meets the power requirements of most domestic properties and small businesses.
It lists the typical reasons customers need that upgrade:
- installing high power equipment such as ground source heat pumps, microgeneration, large motors and welders
- installing any three phase electrical equipment, such as water pumps
- extending a property so it can run more electrical appliances
- converting a building into flats so each one has its own meter
Not every jump in demand needs three phase electricity. UK Power Networks says it’s common for older properties to have 30 or 60 amp fuses, and that it can upgrade these to 80 or 100 amp free of charge. An electrician can tell you whether a bigger fuse will do the job or whether you genuinely need the three phase upgrade.
How does a three phase upgrade work?
UK Power Networks sets out the usual steps. The network is usually underground, so the work normally needs a trench, which it can dig for you or you can arrange yourself on your own land. A meter box and ducting go on an outside wall of the property.
On the day, it finds the nearest electricity cable, usually in the road or pathway, digs down to it, lays a new cable to where your meter will be and reconnects your supply, followed by safety checks. If it did the digging, it says it returns within 48 hours to fill the trench.
Plan the dates around two appointments, because three phase electricity only switches on once the network operator and your supplier have both done their part. If parking outside is tight, UK Power Networks says it may need to apply to the council to suspend parking bays while it works, which is worth knowing early if you’re on a high street.
Three phase electricity upgrade checklist
- Ask an electrician whether a fuse upgrade or three phase electricity is what you need.
- Book the free survey visit with your network operator and get a quote.
- Decide who digs on your land and who fits the meter box.
- Book your energy supplier for the same day the new supply is connected.
- Have any internal wiring finished before the network engineers arrive.
Who pays, and why your energy supplier must be there
The network operator’s quote covers its part of the job. UK Power Networks says every project is different and that it needs to assess the work before giving an exact cost, though it offers an online tool that gives an indication based on what other customers have paid. It says the surveyor visit itself is free, and that filling in the application commits you to nothing beyond that visit and a quote.
The step people miss is the meter. UK Power Networks says your electricity supplier owns the meter, so it is the only company that can move and connect it. It also says you must have booked your supplier to attend on the same day the upgraded supply is connected, and that it can’t do the upgrade otherwise because you’d be left without power. If you’re moving into new premises at the same time, our guide to getting a new business meter connected covers the supplier side of that job.
Because the supplier fits the new meter, it’s also the moment to look at the contract the meter sits on. Ask whether the new meter changes your tariff or standing charge, and check your contract end date while you’re on the phone. Doing nothing at renewal is how a business ends up on rates nobody chose.
Is three phase electricity worth it for a small business?
Three phase electricity is worth it when the work depends on equipment that needs it. A workshop that can’t run its welder, or a farm that wants a bigger pump, has a practical reason to upgrade, and a single phase supply simply won’t carry that load. Our guide to farm energy costs looks at heavy seasonal use of that kind.
It’s less obviously worth it for a business that just wants headroom. The upgrade involves digging, a quote that depends on your site, and coordinating two companies, so start with what your equipment actually needs. If you’re unsure, ask the maker of the machine whether it needs three phase electricity or can run on a single phase supply. Once the supply is in, reading the new meter correctly matters too, and our guide to business meter reading covers the main meter types.
Frequently asked questions about three phase electricity
- Can an electrician install three phase electricity?
- Not the supply itself. The network operator upgrades the connection and the energy supplier fits the meter. An electrician handles the wiring inside your premises.
- How much power does a three phase upgrade give?
- UK Power Networks says its single to three phase upgrade gives up to 70kVA, which it says covers most domestic properties and small businesses.
- Do I have to pay for the survey?
- UK Power Networks says the surveyor visit is free, and you only pay if you accept the quote.
- Why does my energy supplier need to be involved?
- The supplier owns the meter, so only it can move and connect it, and UK Power Networks says it can’t upgrade the supply unless the supplier attends the same day.
Sources
- UK Power Networks, What do you need to upgrade?. The single to three phase upgrade up to 70kVA, the typical reasons for it, and the free 30 or 60 amp to 80 or 100 amp fuse upgrade. No date shown on the page.
- UK Power Networks, What’s involved. Digging and the trench, the meter box and ducting, parking bay suspensions, the connection steps, the 48 hour backfill, and the supplier owning the meter and being the only company that can move and connect it. No date shown on the page.
- UK Power Networks, Cost and time. Costs assessed per project and the cost indication tool based on what other customers have paid. No date shown on the page.
- UK Power Networks, FAQs. The free surveyor visit and what the application commits you to, booking your supplier for the same day, and finishing internal wiring before the engineers arrive. No date shown on the page.
Checked 24 November 2026.